An Illinois Tollway traffic shift has been rescheduled to begin next week on southbound I-57 between 147th Street and the CSX Railroad for ongoing bridge work, as part of work to complete the Tri-State Tollway (I-294)/I-57 Interchange Project.
Now set to begin on June 26, three nights of lane closures will be needed to shift traffic. Southbound I-57 traffic will shift to the left to provide a work zone on the right to complete bridge work. All lanes are scheduled to reopen by 5 a.m. each morning.
Northbound traffic on I-57 is currently shifted into a split configuration with one lane of traffic shifted to the left and two lanes to the right with an additional traffic shift scheduled in July.
Traffic shifts will be needed through summer. Once this work is complete, traffic is scheduled to shift into its final configuration with a fourth lane of traffic open to drivers.
Tollway work is continuing to widen the CSX Railroad Bridge on I-57 as part of the I-294/I-57 Interchange Project. Pavement, and joint work will continue into 2023 at the I-57 bridge over the railroad. In addition, the Illinois Department of Transportation is resurfacing I-57 in this area.
This work is part of the second phase of the I-294/I-57 Interchange Project. In September 2022, the Tollway completed and opened four new ramps to connect southbound I-57 to I-294 and I-294 to northbound I-57, including a flyover ramp bridge. Additional work on this project includes the reconstruction of the I-57 median and the widening of the I-57 mainline, as well as drainage improvements, erosion and sediment control, retaining wall and bridge construction.
Maps and construction information about the Tri-State Tollway (I-294)/I-57 Interchange Project is available in the Project’s section on the Tollway’s website at www.illinoistollway.com.
The $719 million I-294/I-57 Interchange Project is funded by the Illinois Department of Transportation and the Illinois Tollway.
The new interchange is improving travel by providing customers with completed access between the two interstates. For the first time, the new I-294/I-57 Interchange provides motorists with access between I-294 and I-57, including a new interchange at 147th Street. The complete interchange will reduce congestion on local routes, enhance economic development and improve regional mobility. The new interstate-to-interstate connection better serves commuters and freight operators while opening access for local communities.
Electronic message signs and construction signage will be put in place in advance to alert drivers to changes in traffic patterns and construction. Up-to-date information regarding closures will be available in the Illinois Tollway’s Daily Construction Alert. All work is weather dependent.