Several infrastructure and public works projects got the green light at last week’s Palos Heights City Council meeting.
Aldermen on June 3 approved the purchase of a 2025 Chevrolet Silverado for the police department for $48,868 and allocated $17,500 to repaint 179 fire hydrants throughout the city.
During public comment, a resident asked why the city hires contractors to repaint fire hydrants instead of employing teens. Officials said the job requires technical preparation and safety specs that make it unsuitable for youth workers.
The city will spend $18,400 on storm sewer work behind 11850 S. Harlem Avenue and $6,200 to sealcoat and stripe the City Hall parking lot, which was scheduled to be completed June 5.
In Misty Meadows, a valve replacement project was approved at a cost of $13,800. The city will also invest $234,095 in smart meters and replacement parts for its ongoing water meter upgrade program.
Additional funding was approved for engineering and design work across multiple utilities: $14,300 for metal exterior rehab at Misty Meadows; $13,043 for design tied to a new 250,000-gallon water tank; and $6,650 for lift station upgrades along Southwest Highway. The city will spend $32,910 on design work for 2025 sanitary sewer rehabilitation, $34,166 on College Drive water main lining and supply analysis, and up to $101,700 for construction oversight of the 131st Street water main project.
Alderman Dan Brennan said most of the projects remain on schedule and are coming in under budget.
Mayor Bob Straz also gave an update on the long-delayed reopening of 131st Street near Southwest Highway.
A binder coat was applied last week, and the road was expected to re-open this week.
The council also approved hiring a new police officer to serve the area around Shepard High School, which was recently annexed. The school is expected to reimburse the city for the cost of the position.